Essential Tree Surgery - Week commencing Monday 24 November 2014

27th November -

Tree pruning in the drive and car park are complete and the course tree work will be finished today as the cherry picker goes back on Friday 28th.

Members please be aware that work to remove dead and diseased branches from trees lining the golf course entrance driveway, car park perimeter and golf course will be undertaken during this week.

  • Working areas within the car park and entrance drive way are required to position and operate a mobile elevated work platform and space to drop/lower removed tree branches.
  • Work along the driveway will cause possible delays to traffic when temporary closures will be necessary because of the work activity location.
  • Work around the car park will require sections to be closed off daily to create a safe working area and prevent potential damage to private vehicles.

Programme – progress with the work may require some adjustment to the proposed programme therefore please consult the course information line daily for updates.

Riggots Lane – for safety reasons at the road junction we advise members not to exit the golf club via this route!

Monday 24th –

Entrance driveway down towards double bend section
0730 – 11.00 access driveway working therefore significant delays possible;
1130 – 3.30 working within a designated area of the car park;

Tuesday 25th –

Driveway double bend toward club house
0730 – 0900 – designated area of the car park
0900 – 12.00 access driveway working therefore significant delays possible
1230 – 3.30 working within a designated area of the car park;

Wednesday 26th –

As above / course work

Thursday 27th –
Work will be taking place around the golf course - therefore expect individual holes to be closed where tree work is taking place.
work to include: behind 2nd tee, r.h.s. 6th green, rear of 8th tee, l.h.s. 9th, oak tree r.h.s. 11th, oak trees to 16th, 17th & 18th, ash tree to front of ladies 18th tee.

Friday 28th –

as above

We apologise for any inconvenience these works may cause and thank members and golfers for their patience and understanding whilst this work is taking place.